Full and complete electrical re-wire / upgrade for Kerry Group’s Head office and site services.
The installation including an LED Energy efficient lighting upgrade for all corridor and communal areas. High efficiency T5 Dimmable & Non Dimmable lighting upgrade for all other areas.
Other services included:
Cat 6 Data installation c/w 25 year warranty. Fibre Optic Cable Links between the two main Kerry Group Communication Hubs.
As part of our installation it was a requirement that the main server stay operational for the duration of our works (12 months) as this was operating all of Kerry’s data infrastructure.
Client:
Kerry Group: Head Office, Tralee, Co. Kerry
Main Contractors:
Griffin's Brothers
Contract Duration:
12 Months